Project

CONSTRUCTION, OPERATION AND MAINTENANCE OF THE NORTHWESTERN AND SOUTHwestERN BYPASSES IN THE CITY OF HERMOSILLO, STATE OF SONORA.

Sector: Transport


Last Revision

October 16, 2025
 
Short Name of the Project:
0920 Northwestern and Southwestern Bypasses in the City of Hermosillo, State of Sonora
Type of Investment:
Greenfield
Subsector:
Highways / bridges
Asset (s):
 Highway 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

1,182,000,000

Estimated Investment USD:

63,891,891

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Construction,  Operation,  Maintenance

DESCRIPTION

The project consists of the construction, operation, and maintenance of the Northwestern and Southwestern bypasses of Hermosillo.

On April 29, 2025, the Honorable City Council of Hermosillo published a public invitation for a competitive process to grant the concession for the Northwestern and Southwestern bypasses of Hermosillo. Interested parties were allowed to submit proposals for one or both bypasses.

Northwestern Bypass / Awardee: Concesionaria Seri, S.A. de C.V.
The Honorable City Council of Hermosillo granted a concession title for the use, operation, and exploitation of public domain assets for the purpose of constructing the Northwestern Bypass of Hermosillo, approximately 30 km in length, and for operating, managing, preserving, and maintaining the operational sections for a period of 30 years. The operational sections extend from the junction of the road to Mina Nyco with Federal Highway Mexico 15 to the Hermosillo-Aeropuerto CFE ZTH substation (Sections A and B). The section from this substation to the junction with Highway 100 Hermosillo–Bahía de Kino will remain under municipal authority (Section C).

Southwestern Bypass
The Southwestern Bypass extends from the intersection of the extension of Boulevard Quiroga with the Palo Verde Road to Federal Highway Mexico 15 (kilometer 245+800), excluding the grade-separated interchange works with the federal route.

The STATUS information corresponds only to the Northwest Bypass.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Type of Contract
  Concession
Term
30 years
Selection Process
Competitive Procurement Process
Payment Source
Project revenues

STATUS

Stage
  Execution
Substage
  Pre-Execution Activities
RELEVANT DATES
Request for proposals/Announcement April 30, 2025
Proposals Reception May 28, 2025
Ruling June 20, 2025
Contract Signing September 04, 2025
Execution/Construction Starting Date March 01, 2026

GEOLOCATION

State(s)
Sonora   

SPONSOR

Responsive image
Entity
City of Hermosillo
Department
Ayuntamiento de Hermosillo