Gas Pipeline Plan with an Investment of More than 140 billion MXN by 2030
- Of the more than 140 billion MXN, 101.259 billion MXN will be allocated to infrastructure projects and 39.646 billion MXN to maintenance of the national pipeline network.
- Of the total investment, 53 billion MXN correspond to the Federal Electricity Commission (CFE) and 87 billion MXN to the National Center for Natural Gas Control (CENAGAS).
- The investment will supply natural gas to the 13 new CFE power plants and the Development Hubs for Wellbeing (PODECOBI), while also modernizing gas pipelines and other infrastructure.
The Minister of Energy, Luz Elena González Escobar, explained that Mexico currently has 21,149 kilometers (km) of gas pipelines, of which 10,087 km are operated by CENAGAS, 7,666 km by CFE, and 3,396 km by Petróleos Mexicanos (Pemex) and private operators.