Project

Construction and equipment of the Milagros electrical substation and transmission line in the State of Mexico.

Sector: Electricity


Last Revision

July 14, 2026
 
Short Name of the Project:
1083 CFE: Milagros Electrical Substation and Transmission Line.
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 120 MVA, Electric Power Transmission Line 230 KV 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2026: $ 19.3
Contract Scope:
  Construction,  Equipment

DESCRIPTION

CFE: Lump Sum Work and Price Evaluation for the Civil and Electromechanical Construction of the Milagros Electrical Substation, located in the municipality of Nezahualcóyotl, State of Mexico. The substation will consist of two 60 MVA three-phase transformers, two 230 kV SF6 gas-insulated feeders, and 16 23 kV medium-voltage feeders, plus two 9 MVAr capacitor banks. It includes the civil and electromechanical work for the Milagros Transmission Line with the Santa Cruz-Aurora Junction, rated at 230 kV with two circuits, comprising a 0.36 km overhead section with self-supporting towers and aluminum conductors, and a 0.03 km underground transition with polyethylene-insulated copper cable.

Proposals must consider the following national content requirements for the project:
- At least 90% of labor.
- At least 55.29% in materials and permanent installation equipment.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Public Works
Selection Process
International Tender Under Treaty
Payment Source
Budgetary
The budgetary resources required to meet the obligations arising from the execution of the Contract are available in the SAP system, in accordance with the provisions of Section 1.1 of the Tender Specifications.

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Request for proposals/Announcement July 14, 2026
Proposals Reception August 24, 2026
Ruling September 07, 2026
Contract Signing September 22, 2026
Execution/Construction Starting Date September 24, 2026
Term of the Contract November 17, 2027

GEOLOCATION

State(s)
State of Mexico   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Subdirección de Contratación y Servicios
Contact
Mtro. Héctor Omar Leal Nava
E-mail
omar.leal@cfe.mx

ADDITIONAL INFORMATION

Line
Source
Comisión Federal de Electricidad
Description
The Federal Electricity Commission (CFE) is a public company of a social nature that provides electricity, a fundamental service for the development of a nation. It is a productive state enterprise, exclusively owned by the federal government, with legal personality and its own assets.
Portfolio ID or Key
CFE-0004-CACOT-0003-2026