Project

Construction of the Second Line of the Guadalupe Victoria Aqueduct, in Ciudad Victoria, Tamaulipas.

Sector: Water and Environment


Last Revision

June 09, 2025
Short Name of the Project:
0977 Ciudad Victoria II Aqueduct
Type of Investment:
Greenfield
Subsector:
Water Supply
Asset (s):
 Aqueduct 750 litres per second (l/s), Supply Line 54.70 KM, Drinking Water Treatment Plant 1,500 litres per second (l/s), Tank 10,000 m3 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

1,881,180,000

Estimated Investment USD:

101,685,405

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Construction

DESCRIPTION

The project involves the construction of the second line of the Guadalupe Victoria Aqueduct, with a flow rate of 750 l/s, to supply water to 147,000 residents.

The project consists of the following components:
- A 36" diameter pipeline with a length of approximately 54.7 km, with a flow rate of 750 l/s.
- A water intake structure at the Guadalupe Victoria Dam and its respective pumping equipment.
- A water treatment plant with a treatment capacity of 1,500 l/s.
- Pumping stations 1 and 2 for the new pipeline.
- Protective devices.
- A storage tank with a capacity of 10,000 m3.
- An access road.

This project has more than one tender; their links and details can be found in the "More Information" and "Observations" sections once they are identified and published. The information presented here refers to the general characteristics of the project; each tender will have its own specifications and the stage will remain "tendering" when at least one is in progress.

LEGAL AND FINANCIAL STRUCTURE

Selection Process
Public Bid

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Ministry of Finance Registration or equivalent March 18, 2023

GEOLOCATION

State(s)
Tamaulipas   

SPONSOR

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project consists of the construction of the second line of the Guadalupe Victoria Aqueduct, designed to transport 750 liters per second and ensure the potable water supply to the inhabitants of Ciudad Victoria, Tamaulipas. Additionally, it contributes to sustainability by optimizing the use of surface water sources and reducing pressure on aquifers.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
Unidad de Inversiones (SHCP)
Description
Administrative office of the Ministry of Finance that, among other attributions, is responsible for concentrating and managing the pipeline of programs and projects submitted by the entities of the Federal Public Administration.
ID
2316B000036
Website
Responsive image
Source
Compras MX
Description
Compras MX is the Digital Public Procurement Platform of the Federal Public Administration, where anyone can access information about the purchases made by the Government of Mexico to support its operations for the benefit of all.
ID
LO-16-B00-016B00985-N-38-2025
Website
ID
LO-16-B00-016B00985-N-39-2025
Website
ID
LO-16-B00-016B00985-N-40-2025
Website
ID
LO-16-B00-016B00985-N-41-2025
Website
Responsive image
Source
Secretaría de Medio Ambiente y Recursos Naturales
Description
Federal government entity and sectorial authority responsible for establishing the necessary criteria and instruments to guarantee the protection, preservation, and use of natural resources, by developing an environmental policy that ensures sustainable growth.
ID
28TM2022H0038
Permits
ID
28TM2025HD002
Permits, modification water treatment plant
Responsive image
Source
State Government

REMARKS

The description of the works is based on what is indicated in the Investment Unit's registry.

LO-16-B00-016B00985-N-38-2025 / Ruling: June 23, 2025
Construction of the conduction line from the intake works to the pumping plant 1, 1st stage (km 0+000.00 to km 29+889.07).

LO-16-B00-016B00985-N-39-2025 / Proposals Reception: June 23, 2025
Construction of the conduction line from pumping plant 1 to delivery tank (km 29+889.07 to km 54+402.89).

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice