Project

Execution of works: electrical substations and transmission line, in the state of Guerrero.

Sector: Electricity


Last Revision

July 14, 2025
 
Short Name of the Project:
0408 CFE: 338 SLT 2020 Substations, Lines and Distribution Networks (Phase 5)
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 115 KV, Power Station /Electrical Substation 115 KV, Electric Power Transmission Line 23.60 km-c 
Contract Currency:
US Dollars
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Design,  Construction,  Equipment,  Installation

DESCRIPTION

The project primarily consists of the execution of the following works:
- Two substations, S.E. Bonfil and S.E. Papagayo, with a voltage of 115 kV, each with two feeders.
- One transmission line, L.T. Bonfil – Papagayo, with a voltage of 115 kV and a length of 23.6 km (line and circuit).
The scope of work includes the supply of permanent installation equipment and materials, the development of engineering related to electromechanical and civil design, the execution of electromechanical and civil works, pre-operational testing, and the preparation, analysis, and evaluation of the required studies (including geotechnical studies, topographic surveys, and soil resistivity studies), as well as training and capacity-building programs.

- The minimum national labor content required for the execution of the works is 90%, and at least 40% in construction and installation.
- Turnkey lump-sum contract.
- The Federal Electricity Commission (CFE) will not provide any advance payment.
- The maximum contract price CFE considers for awarding the contract is $14,092,040.83 USD.
- Project ID: 1418TOQ0040.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Financed Public Works
Selection Process
International Open Tender
Financing Sources
Private
100 %
MXN
N.A.
USD
N.A.
Payment Source
Budgetary

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Request for proposals/Announcement July 10, 2025
Proposals Reception September 09, 2025
Ruling October 03, 2025
Contract Signing October 24, 2025
Execution/Construction Starting Date October 31, 2025
Term of the Contract April 23, 2027

GEOLOCATION

State(s)
Guerrero   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Subdirección de Contratación y Servicios
Contact
Mtro. Héctor Omar Leal Nava
E-mail
omar.leal@cfe.mx

ADDITIONAL INFORMATION

Responsive image
Source
Comisión Federal de Electricidad
Description
The Federal Electricity Commission (CFE) is a public company of a social nature that provides electricity, a fundamental service for the development of a nation. It is a productive state enterprise, exclusively owned by the federal government, with legal personality and its own assets. It enjoys technical, operational, and managerial autonomy in accordance with the provisions of the Federal Electricity Commission Law.
ID
CFE-0004-CACOA-0002-2025
Tender