Project

WORKS FOR THE UPGRADING OF THE REMEDIOS – 93G00 - EL VIDRIO TRANSMISSION LINE, REPLACEMENT OF PRIMARY EQUIPMENT AND RECALIBRATION OF AUXILIARY BUS (REINFORCEMENT WORKS) OF THE CCC FRANCISCO PÉREZ RÍOS, IN THE STATE OF MEXICO.

Sector: Electricity


Last Revision

April 28, 2026
 
Short Name of the Project:
1067 CFE: Reinforcement Works CCC Francisco Pérez Ríos (Repowering of the Remedios – El Vidrio Line)
Type of Investment:
Brownfield
Subsector:
Transmission / Distribution
Asset (s):
 Electric Power Transmission Line 23.40 km-c 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2026: $ 19.3
Contract Scope:
  Construction,  Equipment,  Installation

DESCRIPTION

The project consists of the construction, installation, and replacement of primary equipment at the 230 kV voltage level and the recalibration of the auxiliary bus; as well as the construction of a 230 kV transmission line with a total length of 23.4 km (line) and 23.4 km (circuit).

The main characteristics of each of the projects are summarized below:
1. Upgrading of the Remedios – 93G00 – El Vidrio Transmission Line
This line will be built overhead, starting at the Remedios 230 kV substation and ending at the El Vidrio substation. It will operate at a nominal voltage of 115 kV and a frequency of 60 Hz. A total of 4.90 km of line will be constructed, with the installation of 6.90 km of circuit.

2. El Vidrio Electrical Substation
Replacement of the 230 kV primary equipment, consisting of six single-phase pad-mounted current transformers, as well as the recalibration of the auxiliary busbar with high-temperature, low-sag ACSS/AW type cable. The work will be carried out at the El Vidrio Substation, an installation currently in operation with a busbar arrangement of one and a half breaker-type I-type transformers at the 230 kV level.

CFE will provide an advance payment of 30% of the total contract amount.

National content requirements for bidders in the execution of the work:
- At least 88.37% of the project cost for materials and permanently installed equipment.
- At least 90% of labor.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Public Works
Selection Process
Open Domestic Bidding
The resources to fulfill the obligations arising from the execution of the Contract will be through the F/311430 Transmission Trust.

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Request for proposals/Announcement April 23, 2026
Proposals Reception May 19, 2026
Ruling June 08, 2026
Contract Signing June 18, 2026
Execution/Construction Starting Date June 22, 2026
Term of the Contract June 16, 2027

GEOLOCATION

State(s)
State of Mexico   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Gerencia de Contrataciones de Obra

ADDITIONAL INFORMATION

Line
Source
Comisión Federal de Electricidad
Description
The Federal Electricity Commission (CFE) is a public company of a social nature that provides electricity, a fundamental service for the development of a nation. It is a productive state enterprise, exclusively owned by the federal government, with legal personality and its own assets.
Portfolio ID or Key
CFE-0004-CACON-0024-2026
Tender