Project

Works at Electrical Substations and Transmission Lines, in the State of Jalisco.

Sector: Electricity


Last Revision

December 18, 2025
 
Short Name of the Project:
1044 CFE: Guadalajara Industrial Substation - Bank 2
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 300 MVA, Power Station /Electrical Substation 69 KV 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2026: $ 19.3
Contract Scope:
  Design,  Construction,  Equipment,  Installation

DESCRIPTION

Lump-sum works contract with price evaluation to carry out the project, which mainly consists of:
- Construction of the Guadalajara Industrial Electrical Substation - Bank 2 + Expansion (300 MVA - 230/69 kV - 0.4 A).
- Construction of the Santa Cruz Electrical Substation Expansion (2A - 69 kV).
- Includes upgrades at seven associated substations, construction of seven 69 kV transmission lines, and recalibration of two transmission lines using high-temperature conductors.

The project scope includes the supply of permanent installation equipment and materials; development of engineering related to electromechanical and civil design concepts; execution of electromechanical and civil works; performance of pre-operational testing; preparation, analysis, and evaluation of required studies (geotechnical studies, topographic surveys, and soil resistivity); and the delivery of training and capacity-building programs.

National content requirements:
- At least 90% labor of national origin.
- At least 39.95% in materials and permanent installation equipment.

CFE will grant an advance payment in each fiscal year during which the works are executed, equivalent to 30% of the amount scheduled to be carried out in each fiscal year.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Public Works
Selection Process
International Tender Under Treaty
Payment Source
Budgetary

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Request for proposals/Announcement December 09, 2025
Proposals Reception February 06, 2026
Ruling February 27, 2026
Contract Signing March 13, 2026
Execution/Construction Starting Date March 16, 2026
Term of the Contract June 08, 2027

GEOLOCATION

State(s)
Jalisco   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Gerencia de Contrataciones de Obra
Contact
Héctor Omar Leal Nava
E-mail
omarl.leal@cfe.mx

ADDITIONAL INFORMATION

Responsive image
Source
Comisión Federal de Electricidad
Description
The Federal Electricity Commission (CFE) is a public company of a social nature that provides electricity, a fundamental service for the development of a nation. It is a productive state enterprise, exclusively owned by the federal government, with legal personality and its own assets.
ID
CFE-0004-CACOT-0005-2025
Tender

Follow the Project

Leave your e-mail to receive updates on this Project.