Project

EXPANSION WORKS FOR THREE ELECTRICAL SUBSTATIONS IN THE STATE OF CHIHUAHUA

Sector: Electricity


Last Revision

November 24, 2025
 
Short Name of the Project:
1038 CFE: Voltage Support for the Mesteñas Region P20-NT1
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
 Power Station /Electrical Substation 80 MVAr, Power Station /Electrical Substation 30 MVAr, Power Station /Electrical Substation 15 MVAr 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Design,  Construction,  Extension,  Equipment

DESCRIPTION

Turnkey, lump-sum construction contract for the execution of the project, which consists of three substation works:
- Oasis Distribution Substation. This substation is currently in operation. The expansion work consists of a static synchronous compensator (STATCOM) rated at 40 MVAr capacitive and 40 MVAr inductive, to be installed at the 115-kV voltage level. The bus arrangement at the 115-kV level is a single bus.
- Mesteñas Transmission Substation. This substation is currently in operation. The expansion work consists of adding a 30-MVAr capacitor bank connected to the 115-kV main bus. The bus arrangement at the 115-kV level is main bus plus auxiliary bus with a tie or transfer circuit breaker.
- El Trébol Distribution Substation. This substation is currently in operation. The expansion work consists of adding a 15-MVAr capacitor bank connected to the 115-kV main bus. The bus arrangement at the 115-kV level is a single bus.

The scope of the project includes the following components: supply of equipment and materials for permanent installation; development of engineering associated with electromechanical and civil design; execution of electromechanical and civil works; performance of pre-operational tests; preparation, analysis, and evaluation of the required studies (geotechnical studies, topographic surveys, and resistivity studies); and the delivery of training and capacity-building programs.

National content of the project:
- At least 90% of the labor must be of national origin.
- Up to 47.10% of the materials and equipment for permanent installation used in the execution of the works.

CFE will grant an advance payment equal to 30% of the total contract amount.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Public Works
Selection Process
Open Domestic Bidding
Payment Source
Budgetary

STATUS

Stage
  Bidding
Substage
  Proposal Development
RELEVANT DATES
Request for proposals/Announcement November 19, 2025
Proposals Reception January 05, 2026
Ruling January 21, 2026
Contract Signing February 18, 2026
Execution/Construction Starting Date February 19, 2026
Term of the Contract September 01, 2027

GEOLOCATION

State(s)
Chihuahua   

SPONSOR

Responsive image
Entity
Comisión Federal de Electricidad
Department
Gerencia de Contrataciones de Obra

ADDITIONAL INFORMATION

Responsive image
Source
Comisión Federal de Electricidad
Description
The Federal Electricity Commission (CFE) is a public company of a social nature that provides electricity, a fundamental service for the development of a nation. It is a productive state enterprise, exclusively owned by the federal government, with legal personality and its own assets. It enjoys technical, operational, and managerial autonomy in accordance with the provisions of the Federal Electricity Commission Law.
ID
CFE-0004-CACON-0022-2025