Project

CONSTRUCTION OF SPORTS CENTER IN ESTACIÓN CENTRAL, "DEPORTIVO 8”, in Durango, Durango.

Sector: Social Infrastructure


Last Revision

November 25, 2024
 
Short Name of the Project:
0956 Sports center at Estacion Central in Durango
Type of Investment:
Greenfield
Subsector:
Culture and Leisure
Asset (s):
 Sports center 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

54,135,435

Estimated Investment USD:

2,926,239

Banobras, Fonadin involvement Banobras/Fonadin involvement

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2025: $ 18.5
Contract Scope:
  Construction

DESCRIPTION

The project consists of the construction of a sports center of the Estación Central Durango Project, considering, but not limited to, the execution of the following works:
- Preliminary Work
- Unpaved lands (soccer and baseball field)
- Soccer area and synthetic grass on the field with net structure and foundation
- Bathrooms and locker rooms, baseball areas and soccer areas (foundation, slab, waterproofing, hydrosanitary installations and sanitary furniture, blacksmithing, electrical installation, finishes
- Trench
- Baseball area (synthetic field)
- Barda Pelotera (foundation, masonry and blacksmithing)
- Dugouts (foundations, masonry, blacksmithing, finishes, electrical installations)
- Home run wall
- Drains in baseball stadium
- Rain vents
- Benches
- Green areas
- Barda
- Pluvial connection (preliminary and sewage)
- Electrical substation
- Soccer field and baseball field lighting
- Foundation for lighting macroposts
- Solar lighting
- Sport stands modules 1, 2 and 3 (foundation, structure, step slabs, ironwork

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Public Works
Selection Process
Open Domestic Bidding
Payment Source
– NA –

STATUS

Stage
  Execution
RELEVANT DATES
Request for proposals/Announcement October 03, 2024
Proposals Reception October 24, 2024
Ruling November 07, 2024
Contract Signing November 11, 2024
Execution/Construction Starting Date December 02, 2024
Term of the Contract May 25, 2026
Contractor
Irkon Holdings y Constructora Quetzal  

GEOLOCATION

State(s)
Durango   

SPONSOR

Responsive image
Entity
State Government
Department
Secretaría de Comunicaciones y Obras Públicas del Estado
Contact
L.A. Cindy Laura Rodríguez Hernández

SUSTAINABLE INFORMATION

PROJECT’S SUSTAINABILITY SUMMARY

The project involves the construction of a Sports Complex within the Estación Central Durango Project, aiming to enhance community access to sports and recreational spaces, while incorporating energy-efficient practices and green areas.

* This summary was prepared based on the methodological framework defined by the Inter-American Development Bank (IDB) in the document entitled: “Attributes and Framework for Sustainable Infrastructure”, which is You can check Here.

Additionally, a brief explanation of the methodology and a summary of the questions applied can be consulted in this Document.

ADDITIONAL INFORMATION

Responsive image
Source
CompraNet
Description
Electronic platform that provides government information of procurements, leases, services, public works, and other related services. Through this platform, the Federal Government ensures the transparency and agility of public procurement. Any interested person can follow the process from beginning to end.
ID
LO-69-023-910003968-N-2-2024
Website

REMARKS

The execution period will be 540 calendar days from the date of start of the work.

Date of contract signing, start date, and execution period, in accordance with the provisions established in the ruling.

The cost of the works indicated in the investment amount includes VAT.

Follow the Project

Leave your e-mail to receive updates on this Project.

 I have read and I accept the Privacy Notice