CONSTRUCTION, EQUIPMENT AND INSTALLATION OF TWO ELECTRIC TRANSMISSION LINES IN THE STATE OF OAXACA.

Sector: Electricity

Last Update
December 01, 2018
Short Name of the Project:
0690 CFE: Energy Supply Transmission Line in Oaxaca and  Huatulco
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
 Electric Power Transmission Line 90 KM-Double Circuit, Electric Power Transmission Line 152 KM-One Circuit 
Contract Currency:
US Dollars
Estimated Investment MXN:

517,536,577

Estimated Investment USD:

25,876,828

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2019: $ 20
Contract Scope:
  Building,  Equipment,  Installation

DESCRIPTION

On December 1st, 2018, Mexico had a federal government administration change. As a consequence, all those projects that are in the pre-investment stage are subject to the confirmation of the new authorities.

Construction of two electric transmission lines. The first of double circuit, in 115 kV and 90 km length; the second of a single circuit, in 230 kV and 152 km length and installation of four monophasic reactors of 28 MVAr each in 230 kV.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Financed Public Works
Term
1 years
Selection Process
  International Open Tender
Financing Sources
Private
100 %
MXN
517,536,577
USD
25,876,828
Payment Source
Budgetary
Financed Public Works Projects (FPW) are funded as follows: The developer is responsible for financing the project during construction, at the end of the works and once the project’s assets are ready to operate, the CFE makes the corresponding payment.

STATUS

Stage
  Preinvestment
Substage
  Studies
RELEVANT DATES
Request for proposals/Announcement
August
2019
Contract Signing February 2020
Execution/Construction Starting Date February 2020
Term of the Contract April 2021

GEOLOCATION

State(s)
Oaxaca   

SPONSOR

Responsive image
Entity
Secretaría de Energía
Department
CFE Transmisión EPS
Contact
Gerardo Aguirre Rivadeneyra
E-mail
gerardo.aguirre@dt.cfe.mx

REMARKS

The project is under review by the Federal Electricity Commission.