Project

EQUIPMENT AND INSTALLATION OF A CAPACITOR IN THE "IZÚCAR DE MATAMOROS" ELECTRIC SUBSTATION IN THE STATE OF PUEBLA.

Sector: Electricity

Last Update
December 01, 2018
Short Name of the Project:
0685 CFE: Izucar de Matamoros Capacitive Compsensation
Type of Investment:
Greenfield
Subsector:
Transmission / Distribution
Asset (s):
 Capacitor 12.50 MVAr 
Contract Currency:
US Dollars
Estimated Investment MXN:

10,796,212

Estimated Investment USD:

539,810

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2019: $ 20
Contract Scope:
  Equipment,  Installation

DESCRIPTION

On December 1st, 2018, Mexico had a federal government administration change. As a consequence, all those projects that are in the pre-investment stage are subject to the confirmation of the new authorities.

Installation of a 12.5 MVAr capacitor in the "Izúcar de Matamoros" electric substation.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public
Type of Contract
  Financed Public Works
Term
1 years
Selection Process
  International Open Tender
Financing Sources
Private
100 %
MXN
10,796,212
USD
539,810
Payment Source
Budgetary
Financed Public Works Projects (FPW) are funded as follows: The developer is responsible for financing the project during construction, at the end of the works and once the project’s assets are ready to operate, the CFE makes the corresponding payment.

STATUS

Stage
  Preinvestment
Substage
  Studies
RELEVANT DATES
Request for proposals/Announcement
February
2019

GEOLOCATION

State(s)
Puebla   

SPONSOR

Responsive image
Entity
Secretaría de Energía
Department
CFE Transmisión EPS
Contact
Gerardo Aguirre Rivadeneyra
E-mail
gerardo.aguirre@dt.cfe.mx

REMARKS

The project is under review by the Federal Electricity Commission.

Follow the Project

Leave your e-mail to receive updates on this Project.