DESIGN, CONSTRUCTION, EQUIPMENT AND INSTALLATION OF AN ELECTRICAL SUBSTATION, TRANSMISSION LINE AND TERMINAL EQUIPMENT IN THE STATE OF COAHUILA.
Sector: Electricity
This project is no longer updated
Last Revision
November 10, 2020
Short Name of the Project:
0240 CFE: Zona La Laguna Electrical Substation
Type of Investment:
Archived Project
Subsector:
Transmission / Distribution
Asset (s):
Power Station /Electrical Substation 375 MVA, Electric Power Transmission Line 41.40 km-c
Contract Currency:
US DollarsEstimated Investment MXN:
445,559,340
Estimated Investment USD:
21,948,736
Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2022: $ 20.3
Contract Scope:
Design, Construction, Equipment, Installation